To have a fully finished product, the bill of materials needs to be received before production. The raw materials required for a particular product might be listed in the bill of materials. Here are the stages involved in making a bill of materials.
The process can be done using the following steps, as follows. Before generating a manufacturing order, the product's components must be configured in the Odoo18 Manufacturing module. Using the Bill of Material function in the Odoo18 Manufacturing module, you can create a list of the components or raw materials required to build the product. The components indicated in the relevant Bill of Material will automatically show up in the Components tab of the manufacturing order when it is created using this Bill of Material.
To create a Bill of Material for a product, select the relevant option from the Manufacturing module's Products menu. The window will show a list of BoM that have already been configured, as seen in the image below.
The list view provides information about the Product, Reference, BoM Type, and Company. Click the New button to start a new BoM.
Please state the Product, Product Variant, Reference, and Quantity that you plan to make in the corresponding fields.
If you are creating this BoM to manufacture this product, you can select the Manufacture this Product option. How to create a bill of materials for a product manufacturing process. You can list each raw material required to create the specified product by using the Add a Line button found under the Components tab. Remember to provide the required amount of the component(s) in the Quantity field.
To complete the product's manufacture, you can now add the operations assigned to the work centers under the Operations tab. You can repeat the current actions assigned to the product by using the matching button in the tab. You can also click the Add a Line option.
There will be a pop-up window explaining the details of the operation. Indicate the work center and the operation to be carried out in the relevant fields. If the operation also applies to the product variations, you can add them in the Apply on Variations section.
Adjust the Duration Computation to suit your requirements. Setting the operation's-duration manually or calculating it using recorded time are your two alternatives. The default duration will show up here. The number of employees required to complete this operation can be specified using the Employee Capacity parameter. The worksheet for the procedure can be added as a text document, Google Slide, or PDF. Complete the space provided with a description of the operation's processes in addition to this.
If you choose the Work Order Dependencies option from the module's Settings menu, Odoo17 will allow you to select the order in which the work orders are finished. By selecting the Operation Dependencies button located under the Miscellaneous tab of the BoM, you can determine the order in which the operations are performed.
Manufacturing Lead Time: This is the average time required for a product to be produced. In the event of a multi-BOM, the wait times for component manufacture will be increased. If the product is being subcontracted, this can be used to determine when components need to be shipped to the subcontractor.
Days required for manufacturing order preparation: Make sure you create and verify production orders sufficiently in advance so you have enough time to produce semi-finished goods or replenish components.
The length of the work order linked to this routing will be measured and reported by Operations Performance Smart. Use the Overview smart button, as shown below,to obtain a broad overview of the BoM.
Included are specifics about the Product, Operations, Quantity, Free to Use/On Hand, Availability, Lead Time, Route, Cost of the Bill of Materials, and product cost.